It is critical that you set up your Energy Probe correctly. Failure to do so can result in missing power data in Streamline, and even damage to your target.
Note
Power profiling is a deprecated feature, and is being removed from Streamline in a future version.
Connect your target to your host through a USB port.
If necessary, install drivers using the standard Windows driver installation.
When first plugging in the Energy Probe on Windows, the LED flashes RED at approximately one second intervals. These red flashes indicate that the USB enumeration has failed and that you must install the driver.
If you are prompted to locate the driver file, select the ARM_EnergyProbe.inf configuration file, which is located in <DS_install_directory>/sw/streamline/energy_meter/energy_probe/.
When you have installed the drivers, and Energy Probe is operating correctly, the LED remains green.
To set it up on Linux Ubuntu, enter the following command:
sudo apt-get install libudev-dev
On Linux Ubuntu, you must do either of the following for Energy Probe to successfully use the device:
Change the permissions of the TTY device by entering the following command:
chmod 777 <tty_location>
Add yourself to the same group as the TTY device by entering the following command:
usermod -a -G <Group_Name User_Name>
dialout is the usual name of the group for the TTY device.
If you attach a probe to the target with the channel wire connector the wrong way around, the LED turns red and blinks. Connecting the channel wire the wrong way round does not damage your target or the Energy Probe but it does not provide useful data. Disconnect all Energy Probes and wait until the LED changes to green. Then reattach them one by one and make sure that you reverse any probe that caused the LED to change to red. When you have attached the Energy Probe correctly, the LED remains green.
Note
If there is low consumption, it is possible that the LED remains red even if the connection is correct. For example, the LED might remain red if the target device is idle.
If your target has headers available for power or energy metering, attach the ground wire, then attach the probes.
Attach the probes.
Make sure that the probe polarity is correct by observing whether the LED changes from green to red. The probe white wire is V+. The black wire is V-.